Close Menu
  • Home
  • AI
  • Art & Style
  • Economy
  • Entertainment
  • International
  • Market
  • Opinion
  • Politics
  • Sports
  • Trump
  • US
  • World
What's Hot

Albanian protesters rally against Kushner-backed resort in sanctuary | Protest news

June 21, 2026

Colombia flirts with the right-wing, Trump-supporting candidate “Tiger” advances to runoff election

June 21, 2026

A century-old rule shuts my daughter out of her own community. A court case could change that

June 20, 2026
Facebook X (Twitter) Instagram
Smart Breaking News on AI, Business, Politics & Global Trends | WhistleBuzz
Facebook X (Twitter) Instagram
  • Home
  • AI
  • Art & Style
  • Economy
  • Entertainment
  • International
  • Market
  • Opinion
  • Politics
  • Sports
  • Trump
  • US
  • World
Smart Breaking News on AI, Business, Politics & Global Trends | WhistleBuzz
Home » Texas data centers increase risk of power outages during extreme winter weather
World

Texas data centers increase risk of power outages during extreme winter weather

Editor-In-ChiefBy Editor-In-ChiefNovember 22, 2025No Comments6 Mins Read
Share Facebook Twitter Pinterest LinkedIn Tumblr Telegram Email Copy Link
Follow Us
Google News Flipboard
Share
Facebook Twitter LinkedIn Pinterest Email


Workers repair power lines in Austin, Texas, United States, Wednesday, February 18, 2021.

Thomas Ryan Allison | Thomas Ryan Allison Bloomberg | Getty Images

The rapid expansion of data centers in Texas has increased demand for electricity in the winter, increasing the risk of supply shortages that could lead to subzero power outages.

The Lone Star State is attracting tremendous demand for data centers, driven by abundant renewable energy and natural gas resources and a business-friendly environment. For example, OpenAI is developing its flagship Stargate campus in Abilene, about 240 miles west of Dallas-Forth Worth. The campus could require up to 1.2 gigawatts of power, equivalent to a large nuclear power plant.

The North American Electric Relibaility Corporation warned this week that data centers’ 24-hour energy consumption will make it more difficult to maintain adequate power supply during extreme demand conditions at subzero temperatures, such as 2021’s devastating winter storm Uri.

NERC said in an analysis released Tuesday that for Texas, “significant increases in load from new data centers and other large industrial end users are driving up winter electricity demand forecasts and contributing to the continued risk of supply shortages.” Although Texas is at increased risk during extreme winter weather, the state’s power grid remains reliable during normal peak demand times, NERC said.

During Uri, demand for home heating surged due to sub-zero temperatures, and at the same time the same weather caused numerous power plants to fail. Texas utility ERCOT ordered rolling blackouts of 20 gigawatts to prevent the system from collapsing, according to a Federal Energy Regulatory Commission report. Most of the power plants that were shut down were running on natural gas.

It was the “largest manually controlled power outage event in U.S. history,” leaving 4.5 million people without power for several days. At least 210 people died in the storm. FERC said most of the deaths were related to power outages, including cases of hypothermia, carbon monoxide poisoning and medical conditions exacerbated by subfreezing temperatures.

Rapid increase in requests to data center

In the years since Uri, Texas has received an incredible amount of requests from data centers, crypto mining facilities, and industrial customers seeking grid connectivity. More than 220 gigawatts of projects have requested connections as of this month, a 170% increase compared to 83 gigawatts of project requests in January, according to data released by ERCOT on Wednesday.

According to ERCOT, about 73% of projects requesting connectivity are data centers.

If all of these projects were actually built, they would be equivalent to the average annual electricity consumption of about 154 million Texas households, according to a CNBC analysis based on 2024 residential power data. However, the Lone Star State’s population is only about 30 million people.

Beth Garza, former head of the ERCOT watchdog, said she was highly skeptical that all of these projects would be built, describing the size of the numbers as “extraordinarily large.” According to ERCOT, more than half of projects do not submit planning studies.

“There’s just not enough on the equipment side or on the consumption side to handle this kind of load. There’s just so much in the world to get to those kinds of numbers,” said Garza, who served as director of ERCOT’s independent market monitor from 2014 to 2019.

Phantom data centers are popping up in grid connection requests across the country as developers sell the same projects to multiple jurisdictions, said John Moura, director of reliability assessments at NERC. This makes it difficult for power companies to predict future demand conditions.

Reliability at risk

The projects that ERCOT has actually approved to connect to the grid are much smaller at 7.5 gigawatts, but that’s still a significant amount of new demand. By comparison, the six-county region of southeastern Pennsylvania that includes Philadelphia, with a population of 1.7 million, had peak demand of about 8.6 gigawatts in 2024, according to the State Electricity Commission.

The balance between supply and demand will become tighter in the winter, and Texas may fall into the red. According to NERC, the state has 92.6 gigawatts of available resources and peak demand could reach around 85.3 gigawatts in an extreme Uri-like scenario.

However, extreme winter weather could reduce available power to about 69.7 gigawatts, leaving a shortage of more than 15 gigawatts. This is due to normal power plant maintenance and forced power plant shutdowns, as well as reduced power capacity due to winter conditions.

“What’s important to understand is the strain we’re seeing,” Moura said. He said NERC’s winter assessment included only data center facilities that reached certain milestones to eliminate speculative projects.

“I can’t overstate how big of a change this is for the electrical industry,” Moura said of the data center request. One solution, he said, is for data centers to exhibit flexibility in power consumption and maintain a balance between supply and demand even in extreme winter scenarios.

In Uri’s case, natural gas plants accounted for 58% of all unplanned outages in Texas, according to FERC. Subzero temperatures reduced gas production, making fuel supplies difficult and causing power transmission problems as power lines fell.

In response to the storm, Texas introduced rules to shore up natural gas infrastructure in preparation for the harsh winter months.

Solar power and battery storage also face challenges when gas plants are shut down on such a large scale, NERC said. Moura said peak demand in the winter occurs in the early morning when sunlight is weak, so batteries may not have had enough time to charge.

With data centers running 24 hours a day, “maintaining sufficient battery charge during prolonged periods of high load, such as during multi-day severe storms like Winter Storm Uri, becomes increasingly difficult,” NERC said in its analysis.

Rob Gramlich, president of power consulting firm Grid Strategies, said “there is a real possibility of power shortages and rolling blackouts in certain regions” of the U.S. over the next few years as demand from data centers and other facilities exceeds supply. “They are unacceptable to anyone in the United States.”

Garza said he is confident that reliable demand from data centers will bring new supply. “Plants love opportunities like that,” she said. “My expectation is that this will attract additional private capital investment to meet supply needs.”



Source link

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Editor-In-Chief
  • Website

Related Posts

British Prime Minister Starmer reportedly ready to resign, sources say he is focused on work

June 20, 2026

MAHA SNAP regulations on junk food could change spending

June 20, 2026

The budget airline model in the U.S. is running out of runway

June 20, 2026
Add A Comment

Comments are closed.

News

Albanian protesters rally against Kushner-backed resort in sanctuary | Protest news

By Editor-In-ChiefJune 21, 2026

Published June 21, 2026June 21, 2026Thousands of protesters marched through Albania’s capital, Tirana, in one…

President Trump vows Iran will not charge Strait of Hormuz tolls, but US says it may | Donald Trump News

June 20, 2026

‘You could have been the greatest’: President Trump faces Israeli anger over Iran deal | US-Israel war on Iran News

June 20, 2026
Top Trending

Signal’s Meredith Whitaker says to remember that AI chatbots are ‘not your friends’

By Editor-In-ChiefJune 20, 2026

When asked about the privacy implications of chatbots like ChatGPT and Claude,…

In the Weights is a new AI-centric vanity search

By Editor-In-ChiefJune 20, 2026

Anyone who has searched on Google lately knows that search results aren’t…

How to turn off AI in Google Docs

By Editor-In-ChiefJune 19, 2026

It happened to me. When I opened Google Docs to write an…

Subscribe to News

Subscribe to our newsletter and never miss our latest news

Welcome to WhistleBuzz.com (“we,” “our,” or “us”). Your privacy is important to us. This Privacy Policy explains how we collect, use, disclose, and safeguard your information when you visit our website https://whistlebuzz.com/ (the “Site”). Please read this policy carefully to understand our views and practices regarding your personal data and how we will treat it.

Facebook X (Twitter) Instagram Pinterest YouTube

Subscribe to Updates

Subscribe to our newsletter and never miss our latest news

Facebook X (Twitter) Instagram Pinterest
  • Home
  • Advertise With Us
  • Contact US
  • DMCA Policy
  • Privacy Policy
  • Terms & Conditions
  • About US
© 2026 whistlebuzz. Designed by whistlebuzz.

Type above and press Enter to search. Press Esc to cancel.